Main deliverables/outputs include the following
  • Topographical surveys and geotechnical investigations
  • Updating of existing Engineering designs of selected facilities
  • Production of detailed architectural and structural drawings
  • Design of appropriate low-cost public and neighbourhood, school toilet blocks and solid waste skip holding bay, and priority sullage and drainage works
  • Update of designs & block drawings, costs and procurement of works/services
  • Construction supervision & preparation of Facilities Operation and Maintenance Handbook (FOM-H)
  • General Contract Management Reporting
  • Post-Construction Services
  • Preparation of Facilities Management Plans (FMP)